Stansted Airport

July 2018

In July 2018 imus were appointed by LPL to act as their lead designer for the development of the second phase of MAGs master plan to expand the airport capacity by constructing a new arrivals terminal building housing customs security and baggage reclaim whilst reconfiguring the existing ‘Fosters’ terminal to accommodate new check-in and central search areas and a significantly increased international departures lounge area.

The focus of this work centres around the next wave of check-in desks and the coordination of the baggage conveyor connections. This includes increased provison for UK Border Force and a reconfiguration of the security search channel.

Further retail demolition and relocation design has taken place to facilitate these works. The end goal being the enabling of progression of the new terminal building whilst maintaining a fully operational airport service.

Back to projects