Stansted Airport

April 2018

In October 2017 imus were appointed by LPL to act as the lead designer for the design development and delivery of the first phase of the Stansted Airport ‘Shoreline’ project.

This forms the initial step in MAGs master plan to expand the airport capacity by constructing a new arrivals terminal building housing Customs security and baggage reclaim whilst reconfiguring the existing ‘Fosters’ terminal to accommodate new check-in and central search areas and a significantly increased international departures lounge area.

imus completed the detailed design RIBA Stage 4/5 for the demolition and decanting of airport critical facilities & users and the installation of the first wave of new check-in desks on programme. Construction completed in readiness for the Easter peak passenger departures.